1.
Breaking up or
scarification of the soil
base with a grader
2.
Wetting of the soil
using a tanker truck
3.
Application of OFB Bind
& Seal from a spray
nozzle on the back of
a tanker truck
4.
Grading to evenly
distribute the product
and mix the treated soil
5.
Compaction of the
treated soil using
a roller
6.
Final application of
OFB Bind & Seal to
seal the treated road
APPLICATION
of ofb bind & seal
2. Wetting of the soil prior to
application of OFB Bind and Seal
APPLICATION
of ofb bind & seal
3. Application of OFB Bind and Seal from spray nozzle on tanker truck
APPLICATION
of ofb bind & seal
4. Mixing of soil treated with OFB Bind and Seal with grader
APPLICATION
of ofb bind & seal
5. Compaction and application
of final seal coat of OFB Bind and Seal
APPLICATION
of ofb bind & seal
2. Wetting of the soil prior to
application of OFB Bind and Seal
APPLICATION
of ofb bind & seal
3. Application of OFB Bind and Seal from spray nozzle on tanker truck
APPLICATION
of ofb bind & seal
4. Mixing of soil treated with OFB Bind and Seal with grader
APPLICATION
of ofb bind & seal
5. Compaction and application
of final seal coat of OFB Bind and Seal